$0.14
Milestones
4 of 4 delivered · $1,843.38 expected · $1,320.71 measured
Roadmap changes since the first backing
No roadmap changes since the first backing.
-
01OCR de fatura impressaaudited
delivered on May 28, 2026 · confidence 92%
Entrega textual do marco 1 de Extrato Fácil.
- Expected
- $460.85
- Actual
- $334.48
- Deviation
- spent 27% less than planned
- Evidence
- see evidence
What counts as delivered
- Evidencia publica no repositorio
- Nota de entrega do criador
Designated commit 2026-05-27
-
02Categorização automáticaaudited
delivered on Jul 7, 2026 · confidence 93%
Entrega textual do marco 2 de Extrato Fácil.
- Expected
- $460.85
- Actual
- $310.27
- Deviation
- spent 33% less than planned
- Evidence
- see evidence
What counts as delivered
- Evidencia publica no repositorio
- Nota de entrega do criador
Designated commit 2026-07-06
-
03Comparação mês a mêsaudited
delivered on Aug 21, 2026 · confidence 88%
Entrega textual do marco 3 de Extrato Fácil.
- Expected
- $460.85
- Actual
- $399.99
- Deviation
- spent 13% less than planned
- Evidence
- see evidence
What counts as delivered
- Evidencia publica no repositorio
- Nota de entrega do criador
Designated commit 2026-08-20
-
04Exportação para planilhaassessed
delivered on Sep 23, 2026 · confidence 92%
Entrega textual do marco 4 de Extrato Fácil.
- Expected
- $460.85
- Actual
- $275.97
- Deviation
- spent 40% less than planned
- Evidence
- see evidence
What counts as delivered
- Evidencia publica no repositorio
- Nota de entrega do criador
Designated commit 2026-09-22